CR – Nov 2021 – L3 – Q2b – IFRS 15: Revenue from Contracts with Customers

Determine how Barikisu Ltd should account for revenue and costs related to a construction contract with a customer under IFRS 15.

On 1 January 2020, Barikisu Ltd (Barikisu) entered into a contract with a customer to construct a specialised building for a consideration of GH¢2 million plus a bonus of GH¢0.4 million if the building is completed within 18 months. The estimated cost to construct the building is GH¢1.5 million. If the customer terminates the contract, Barikisu can demand payment for the cost incurred to date plus a mark-up of 30%. However, on 1 January 2020, due to factors outside of its control, such as the weather and regulatory approval, Barikisu is not sure whether the bonus will be achieved.

As at 31 December 2020, Barikisu has incurred a cost of GH¢1.0 million. They are still unsure as to whether the bonus target will be met. Therefore, Barikisu decided to measure progress towards completion based on the cost incurred. To date, Barikisu has received GH¢1 million from the customer.

Required:

Recommend to the directors of Barikisu how this transaction should be accounted for in the financial statements for the year ended 31 December 2020 in accordance with relevant International Financial Reporting Standards (IFRS).

Login or create a free account to see answers

Find Related Questions by Tags, levels, etc.

Report an error

You're reporting an error for "CR – Nov 2021 – L3 – Q2b – IFRS 15: Revenue from Contracts with Customers"

CR – Nov 2021 – L3 – Q2b – IFRS 15: Revenue from Contracts with Customers

Determine how Barikisu Ltd should account for revenue and costs related to a construction contract with a customer under IFRS 15.

On 1 January 2020, Barikisu Ltd (Barikisu) entered into a contract with a customer to construct a specialised building for a consideration of GH¢2 million plus a bonus of GH¢0.4 million if the building is completed within 18 months. The estimated cost to construct the building is GH¢1.5 million. If the customer terminates the contract, Barikisu can demand payment for the cost incurred to date plus a mark-up of 30%. However, on 1 January 2020, due to factors outside of its control, such as the weather and regulatory approval, Barikisu is not sure whether the bonus will be achieved.

As at 31 December 2020, Barikisu has incurred a cost of GH¢1.0 million. They are still unsure as to whether the bonus target will be met. Therefore, Barikisu decided to measure progress towards completion based on the cost incurred. To date, Barikisu has received GH¢1 million from the customer.

Required:

Recommend to the directors of Barikisu how this transaction should be accounted for in the financial statements for the year ended 31 December 2020 in accordance with relevant International Financial Reporting Standards (IFRS).

Login or create a free account to see answers

Find Related Questions by Tags, levels, etc.

Report an error

You're reporting an error for "CR – Nov 2021 – L3 – Q2b – IFRS 15: Revenue from Contracts with Customers"

error: Content is protected !!
Oops!

This feature is only available in selected plans.

Click on the login button below to login if you’re already subscribed to a plan or click on the upgrade button below to upgrade your current plan.

If you’re not subscribed to a plan, click on the button below to choose a plan