PM – Nov 2015 – L2 – Q2 – Standard Costing and Variance Analysis

Calculate material price and usage planning and operational variances for wheat used in baking cake and bread, and discuss the benefits of these variances.

Pestel Limited produces cake and bread which it supplies to a major supermarket in
Abuja. It holds no inventories because it adopts the Just-In-Time (JIT) system.
The standard cost of the wheat used in baking the products is N200 per kg. Each piece
of cake uses 0.5kg of wheat while each loaf of bread uses 2kg of wheat.
The production levels for cake and bread for the month of October were as follows:

The actual cost of wheat in October was N232 per kg. 496,000kg of wheat was used to
bake the bread and 190,000kg was used to bake the cake.
The global prices of wheat increased by 18% in the month of October.

At the beginning of the month, the supermarket group made an expected request for an
immediate shape change to the cake resulting in 5% more wheat than previously
required. This change also brought about production delays which caused a reduction in
production by 20,000 units of cake in that month. The production director is given the
task of purchasing relevant input materials and any production request which occur,
although he does not take responsibility for setting standard costs.
Required:

(a) Compute the following variances for the month of October for each product and in total:

(i) Material price planning variances, (4 Marks)

(ii) Material price operational variances. (4 Marks)

(iii) Material usage planning variances, (4 Marks)

(iv) Material usage operational variances (4 Marks)

(b) Discuss the benefits of planning and operational variances to a management accountant. (4 Marks)

Login or create a free account to see answers

Find Related Questions by Tags, levels, etc.

Report an error

You're reporting an error for "PM – Nov 2015 – L2 – Q2 – Standard Costing and Variance Analysis"

PM – Nov 2015 – L2 – Q2 – Standard Costing and Variance Analysis

Calculate material price and usage planning and operational variances for wheat used in baking cake and bread, and discuss the benefits of these variances.

Pestel Limited produces cake and bread which it supplies to a major supermarket in
Abuja. It holds no inventories because it adopts the Just-In-Time (JIT) system.
The standard cost of the wheat used in baking the products is N200 per kg. Each piece
of cake uses 0.5kg of wheat while each loaf of bread uses 2kg of wheat.
The production levels for cake and bread for the month of October were as follows:

The actual cost of wheat in October was N232 per kg. 496,000kg of wheat was used to
bake the bread and 190,000kg was used to bake the cake.
The global prices of wheat increased by 18% in the month of October.

At the beginning of the month, the supermarket group made an expected request for an
immediate shape change to the cake resulting in 5% more wheat than previously
required. This change also brought about production delays which caused a reduction in
production by 20,000 units of cake in that month. The production director is given the
task of purchasing relevant input materials and any production request which occur,
although he does not take responsibility for setting standard costs.
Required:

(a) Compute the following variances for the month of October for each product and in total:

(i) Material price planning variances, (4 Marks)

(ii) Material price operational variances. (4 Marks)

(iii) Material usage planning variances, (4 Marks)

(iv) Material usage operational variances (4 Marks)

(b) Discuss the benefits of planning and operational variances to a management accountant. (4 Marks)

Login or create a free account to see answers

Find Related Questions by Tags, levels, etc.

Report an error

You're reporting an error for "PM – Nov 2015 – L2 – Q2 – Standard Costing and Variance Analysis"

error: Content is protected !!
Oops!

This feature is only available in selected plans.

Click on the login button below to login if you’re already subscribed to a plan or click on the upgrade button below to upgrade your current plan.

If you’re not subscribed to a plan, click on the button below to choose a plan