QTB – May 2017 – L1 – SB – Q2b – Data Collection and Analysis
Determine angles for pie chart representation and complete a project network diagram with project duration.
Question
i. The monthly expenditure (₦’000) of a household on some items are given as follows:
Item | Expenditure (₦’000) |
---|---|
Food | 50 |
Transport | 25 |
Utilities | 35 |
Miscellaneous | 10 |
Determine the angle which will represent each item on a pie chart. (6 Marks)
ii. The activities needed to complete a project with their durations (in weeks) are given below:
Activity | Preceding Activity | Duration (weeks) |
---|---|---|
A | – | 4 |
B | – | 6 |
C | A | 8 |
D | B | 12 |
E | B | 11 |
F | C, D | 9 |
You are required to draw the activity-on-arrow network diagram for the project and determine the duration of the project. (4 Marks)