SCS – Nov 2023 – L3 – Q4c – Controlling Risk
Identifying and explaining four production resource planning needs to manage production capacity challenges.
Question
It is evident that NSL has capacity challenges, and this has impacted the decision to expand to other markets. To succeed, NSL must plan to obtain the resources that it will need each year to meet the required capacity levels.
Required:
Identify and explain FOUR (4) production resource planning needs that NSL should focus on to effectively manage its production capacity challenges.
(6 marks)