FM – MAY 2019 – L2 – Q2a – Capital structure

Calculate the current market capitalization of M&E Ltd and the Weighted Average Cost of Capital (WACC) prior to financing a new project.

Question:
M&E Ltd, recognized as the leader in steel manufacturing, has received an invitation to supply steel for the construction of rail lines to connect the ECOWAS countries, starting from Nigeria. The contract will be for 10 years, and management is considering appraising the investment to enable them to present their proposals for the contract. The following information was extracted from the recently published accounts of M&E Ltd:

GH¢ ‘000
Equity Shares (1,000,000 shares) 70,000
15% Preference shares 50,000
10% (Bonds irredeemable) 30,000
Total 150,000

The Treasury unit of M&E Ltd has estimated that it will require GH¢ 10 million to finance the new project. The total amount would be raised through 10% Irredeemable bonds at the current market price. The cost of Preference shares and Bonds will not change, but equity shareholders will demand an increase of 20% on the current cost of equity.

M&E Ltd has a beta of 0.8, the market risk premium for the steel industry is 6.25%, and the Government of Ghana Bond rate is 20%. The current market price for Irredeemable Bonds of GH¢1,000 nominal value is GH¢850.

M&E Ltd’s dividend policy is to pay constant dividends, and this policy will not change in the foreseeable future. The recent dividend paid was GH¢20 per share. M&E Ltd is a Free Zones Company and therefore pays tax at a rate of 8%.

Required:

i) Calculate the current market capitalization of M&E Ltd. (5 marks)

ii) Calculate the Weighted Average Cost of Capital (WACC) prior to the consideration of the finance for the proposed project. (9 marks)

(Total: 14 marks)

Login or create a free account to see answers

Find Related Questions by Tags, levels, etc.

Report an error

You're reporting an error for "FM – MAY 2019 – L2 – Q2a – Capital structure"

FM – MAY 2019 – L2 – Q2a – Capital structure

Calculate the current market capitalization of M&E Ltd and the Weighted Average Cost of Capital (WACC) prior to financing a new project.

Question:
M&E Ltd, recognized as the leader in steel manufacturing, has received an invitation to supply steel for the construction of rail lines to connect the ECOWAS countries, starting from Nigeria. The contract will be for 10 years, and management is considering appraising the investment to enable them to present their proposals for the contract. The following information was extracted from the recently published accounts of M&E Ltd:

GH¢ ‘000
Equity Shares (1,000,000 shares) 70,000
15% Preference shares 50,000
10% (Bonds irredeemable) 30,000
Total 150,000

The Treasury unit of M&E Ltd has estimated that it will require GH¢ 10 million to finance the new project. The total amount would be raised through 10% Irredeemable bonds at the current market price. The cost of Preference shares and Bonds will not change, but equity shareholders will demand an increase of 20% on the current cost of equity.

M&E Ltd has a beta of 0.8, the market risk premium for the steel industry is 6.25%, and the Government of Ghana Bond rate is 20%. The current market price for Irredeemable Bonds of GH¢1,000 nominal value is GH¢850.

M&E Ltd’s dividend policy is to pay constant dividends, and this policy will not change in the foreseeable future. The recent dividend paid was GH¢20 per share. M&E Ltd is a Free Zones Company and therefore pays tax at a rate of 8%.

Required:

i) Calculate the current market capitalization of M&E Ltd. (5 marks)

ii) Calculate the Weighted Average Cost of Capital (WACC) prior to the consideration of the finance for the proposed project. (9 marks)

(Total: 14 marks)

Login or create a free account to see answers

Find Related Questions by Tags, levels, etc.

Report an error

You're reporting an error for "FM – MAY 2019 – L2 – Q2a – Capital structure"

error: Content is protected !!
Oops!

This feature is only available in selected plans.

Click on the login button below to login if you’re already subscribed to a plan or click on the upgrade button below to upgrade your current plan.

If you’re not subscribed to a plan, click on the button below to choose a plan