Question Tag: Critical Path Method

Search 500 + past questions and counting.
  • Filter by Professional Bodies

  • Filter by Subject

  • Filter by Series

  • Filter by Topics

  • Filter by Levels

QTB – May 2017 – L1 – SB – Q2b – Data Collection and Analysis

Determine angles for pie chart representation and complete a project network diagram with project duration.

i. The monthly expenditure (₦’000) of a household on some items are given as follows:

Item Expenditure (₦’000)
Food 50
Transport 25
Utilities 35
Miscellaneous 10

Determine the angle which will represent each item on a pie chart. (6 Marks)

ii. The activities needed to complete a project with their durations (in weeks) are given below:

Activity Preceding Activity Duration (weeks)
A 4
B 6
C A 8
D B 12
E B 11
F C, D 9

You are required to draw the activity-on-arrow network diagram for the project and determine the duration of the project. (4 Marks)

Login or create a free account to see answers

Find Related Questions by Tags, levels, etc.

Report an error

You're reporting an error for "QTB – May 2017 – L1 – SB – Q2b – Data Collection and Analysis"

QTB – May 2017 – L1 – SB – Q2b – Data Collection and Analysis

Determine angles for pie chart representation and complete a project network diagram with project duration.

i. The monthly expenditure (₦’000) of a household on some items are given as follows:

Item Expenditure (₦’000)
Food 50
Transport 25
Utilities 35
Miscellaneous 10

Determine the angle which will represent each item on a pie chart. (6 Marks)

ii. The activities needed to complete a project with their durations (in weeks) are given below:

Activity Preceding Activity Duration (weeks)
A 4
B 6
C A 8
D B 12
E B 11
F C, D 9

You are required to draw the activity-on-arrow network diagram for the project and determine the duration of the project. (4 Marks)

Login or create a free account to see answers

Find Related Questions by Tags, levels, etc.

Report an error

You're reporting an error for "QTB – May 2017 – L1 – SB – Q2b – Data Collection and Analysis"

error: Content is protected !!
Oops!

This feature is only available in selected plans.

Click on the login button below to login if you’re already subscribed to a plan or click on the upgrade button below to upgrade your current plan.

If you’re not subscribed to a plan, click on the button below to choose a plan